NEW QUESTION 13
The system status of a WBS element is created (CRTD). Which business process is allowed for this WBS element?

  • A. Calculation of actual values
  • B. Activity allocation
  • C. Goods receipt for purchase orders
  • D. Creation of purchase orders

Answer: D

 

NEW QUESTION 14
You have assigned a material to a network activity and want to determine the requirement date related to this activity. What set of dates do you have to maintain?

  • A. Basic dates of the network activity
  • B. Forecast dates of the WBS
  • C. Basic dates of the WBS
  • D. Actual dates of the network activity

Answer: A

 

NEW QUESTION 15
You have created an internally-processed network activity, and assigned a work center and the work.
After saving, you discover that no planned costs are displayed in the cost element report for the activity.
What could be the reason? Note: There are 3 correct Answers to this question.

  • A. The activity output price for the activity type and cost center assigned to the work center is not maintained.
  • B. The duration is missing in the activity.
  • C. The formula for costing in the work center is incorrect.
  • D. The Determine Costs indicator in the network header rules out planned cost calculation.
  • E. Integrated planning for the network is active.

Answer: A,B,D

 

NEW QUESTION 16
Which organizational structures are required for network activities? Note: There are 3 correct Answers to this question.

  • A. Plant
  • B. Company code
  • C. Operating concern
  • D. Sales organization
  • E. Controlling area

Answer: A,B,E

 

NEW QUESTION 17
A component is assigned to a network activity. What are the prerequisites to generate project stock reservations? Note: There are 3 correct Answers to this question.

  • A. The Project Stock indicator is set in the project definition (non-valuated or valuated).
  • B. The network is assigned to a sales order item.
  • C. The material master of the component must permit project stock management.
  • D. The network activity is assigned to a WBS element.
  • E. A procurement indicator must be assigned to the activity.

Answer: A,C,E

 

NEW QUESTION 18
Which statement is valid regarding networks? Note: There are 2 correct Answers to this question.

  • A. Relationships can be used to connect activities of different networks.
  • B. A network can be activity-account-assigned and header-account-assigned.
  • C. A network activity can be assigned to several WBS elements.
  • D. Material components can be assigned to activity elements.

Answer: A,B

 

NEW QUESTION 19
Where do you control whether a project stock is managed as valuated or non-valuated project stock?

  • A. In the material master
  • B. In the network activity
  • C. In the project definition
  • D. In the WBS element

Answer: C

 

NEW QUESTION 20
In your project, you work with a network and external activities. You have created a purchase requisition. The corresponding purchase order is created as well. Now, you increase the quantity of the external activity. How does the system support this scenario?

  • A. A workflow can be triggered to inform the purchasing group.
  • B. The system automatically creates a new purchase requisition with the difference to the original quantity.
  • C. The purchase order can be updated in Goods Receipt for Purchase Order (MIGO).
  • D. The purchase order is updated automatically to match the new quantity while saving the project.

Answer: A

 

NEW QUESTION 21
What are some of the possible functions in user status profiles? Note: There are 2 correct Answers to this question.

  • A. Allow business processes forbidden by SAP system status.
  • B. Ensure user status must always be set manually.
  • C. Restrict setting user status for individual users.
  • D. Utilize priorities for setting the user status.

Answer: C,D

 

NEW QUESTION 22
What functions are available for period end closing in SAP Project System? Note: There are 3 correct Answers to this question.

  • A. Confirmations
  • B. Settlement
  • C. Results analysis
  • D. Progress analysis
  • E. Milestone trend analysis

Answer: B,C,D

 

NEW QUESTION 23
Where do you maintain the length of the project ID?

  • A. Project profile
  • B. Project type
  • C. Special characters
  • D. Project coding mask

Answer: D

 

NEW QUESTION 24
What functionality can you perform with activity elements?

  • A. Assign work centers and capacities
  • B. Schedule WBS elements
  • C. Assign material
  • D. Create relationships

Answer: D

 

NEW QUESTION 25
What business transactions can be used with Project-Oriented Procurement (ProMan)? Note: There are
3 correct Answers to this question.

  • A. Generate delivery
  • B. Generate purchase requisition
  • C. Confirm production order
  • D. Stock transfer posting
  • E. Cancel goods issue

Answer: A,B,D

 

NEW QUESTION 26
A customer needs to analyse the capacity requirements of their network activities. Which reports do you recommend? Note: There are 2 correct Answers to this question.

  • A. Cost element reports
  • B. Hierarchical reports
  • C. Resource reports
  • D. Structure information system reports

Answer: D

 

NEW QUESTION 27
Which of the following data can be maintained in a standard network? Note: There are 3 correct Answers to this question.

  • A. Document information records
  • B. Basic dates for activities
  • C. Relationships
  • D. Internally processed activities
  • E. Material components

Answer: C,D,E

 

NEW QUESTION 28
You want to make sure that certain tasks must start on a given date. Where can you maintain constraints for start dates?

  • A. Network header
  • B. Milestone
  • C. Activity
  • D. Activity element

Answer: C

 

NEW QUESTION 29
Your customer wants to use requirements grouping in SAP Project System. What are the prerequisites for requirements grouping of materials? Note: There are 2 correct Answers to this question.

  • A. The procurement type of the material must be internal.
  • B. An MRP group must be assigned.
  • C. The materials must allow sales order or project stock.
  • D. The exact lot size procedure must be used.

Answer: B,C

 

NEW QUESTION 30
......


SAP C_TS412_1909 Exam Description:

The "SAP Certified Application Associate - SAP S/4HANA Project Systems" certification exam verifies that the candidate has the fundamental and core knowledge in the area of sourcing and procurement required for the consultant profile. This certificate proves that the candidate has an overall understanding and can implement the knowledge practically in projects to contribute to the success of the planning and implementation phases in a mentored role. Previous project experience is not necessarily a prerequisite to pass this exam.

 